Self Store, Drive Thru & Retail Development, Bristol

Following collaboration with the client and design team Tercon submitted a Stage 1 cost plan. Following this Tercon were commissioned to develop design and a detailed project cost during a Stage 2 Preconstruction Phase.

Tercon were subsequently awarded the construction contract under a JCT Design and Build form with the initial design team retained.

The project involved the construction of a Self-Storage warehouse, 5 retail units and a Drive-Thru Starbucks coffee shop. The site access road was shared with a school requiring careful attention to segregation, control of traffic and liaison with the school staff.

Key elements of work

  • Site preparation and enabling works including asbestos removal, on-site crushing of hard material arising and an extensive section of king-post retaining  wall with precast concrete infill panels in a party boundary wall
  • Shell construction of five retail units and a detached Starbucks coffee shop unit with Drive-Thru facilities
  • Shell construction of a large self-store unit with vibropile ground improvement
  • An extensive series of S278 highway works to a major city trunk road, requiring extensive mains services alterations and diversions and phased traffic management arrangements
  • Construction of a new access road, footpaths and drainage which was shared with a live school main access. All estate access, circulation, parking with hard and soft landscaping

Project Details

CLIENT

Storage Giant

PROJECT TYPE
VALUE

Not disclosed

ROLE

Design & Build Main Contractor